71 Google Reviews
    07 3180 8041

    Pre Pour Slab Inspection

    Inspect steel reinforcement, formwork, and services before the concrete pour. Your foundation for peace of mind.

    Book before concrete pour — usually 24–48 hours notice

    $550Same-day report · QBCC 1318443

    Why Pre-Pour Inspections Are Essential

    Once concrete is poured, there's no going back. A pre-pour inspection verifies that reinforcement, formwork, services and termite management are all correct before the truck arrives — while a steel fixer or plumber can still come back and fix what we flag without delaying the pour.

    We check that steel reinforcement is correctly positioned against the engineer's drawings, bar chairs are spaced and sized to give the cover specified in AS 3600 Concrete Structures, formwork is rigid enough to hold its set-out under the load of wet concrete, and plumbing and electrical penetrations are in the locations the trade drawings call for.

    Mistakes discovered after the pour require expensive cutting, drilling, epoxy injection or in serious cases full demolition. Prevention is cheaper than rectification at every stage.

    What's Included

    • Steel reinforcement mesh inspection
    • Bar chair spacing and coverage
    • Edge beam reinforcement verification
    • Formwork alignment and bracing
    • Plumbing penetration locations
    • Electrical conduit placement
    • Vapour barrier / membrane check
    • Termite barrier (AS 3660.1) verification
    • Same-day PDF report with photos
    From $550

    Includes GST

    Critical Elements We Verify

    Steel Mesh

    Correct placement and lapping

    Bar Chairs

    Adequate support and spacing

    Formwork

    Level and correctly positioned

    Services

    Penetrations in right locations

    What we look for on a pre-pour inspection

    A residential slab on a Brisbane or South East Queensland site is engineered for a specific soil class — typically M, H1 or H2 reactive clay across the Moreton Bay and Logan corridors. The reinforcement layout, edge beam depth, internal beam locations and concrete cover are all called up on the engineer's drawings, and small departures during the steel fix can compound into cracking, edge curl or termite vulnerability years later. Our pre-pour checklist works through each of these systematically:

    • Formwork alignment and rigidity — set-out checked against the engineer's plan, bracing adequate to hold the perimeter under the load of wet concrete, no gaps where mortar could escape.
    • Reinforcement steel placement — top and bottom mesh laps meet the minimum 225 mm overlap, edge beam cages have the correct number of bars and ligatures at the spacing called up, trench mesh is continuous around penetrations.
    • Compliance with engineer's drawings — bar diameters and grades match the schedule, additional bars over internal beams or load points are present, any site-specific variations have been signed off by the engineer in writing.
    • Soil compaction and base preparation — fill is properly compacted with no soft spots, sub-base is graded and clean, no organic material or loose spoil under the membrane.
    • Plumbing penetration positions — sewer and waste penetrations match the hydraulic drawings to ±25 mm, sleeves are correctly sized so the slab is not loaded onto pipework, AS/NZS 3500 clearances around bends are respected.
    • Termite barrier installation — perimeter and penetration system installed per AS 3660.1, joins lapped and sealed, no damage from later trades, manufacturer's installation requirements followed exactly so the warranty is enforceable.
    • Concrete cover requirements per AS 3600 — bar chairs sized so the bottom mesh sits at the cover required for the exposure classification (typically 30–40 mm for residential slabs on grade in SEQ), chairs spaced close enough that the mesh does not sag below cover between supports.
    • Vapour barrier and membrane — continuous under the slab, taped at all joins and penetrations, no tears from foot traffic during the steel fix.

    Common defects we find at pre-pour

    Most pre-pour inspections in Brisbane new builds turn up two or three rectifiable items. Builders run a lot of jobs in parallel and steel fixers move between sites quickly, so small things get missed. The most common items in our reports across the last twelve months are:

    • Bar chairs spaced too far apart — mesh sags between supports and ends up with less than the required cover at the centre of the panel, the most common cause of corrosion-related cracking five to ten years post-pour.
    • Missing ligatures in edge beams — the schedule calls for ligatures at 200 mm centres around penetrations and corners; in practice we frequently find one or two missing or spaced at 400 mm.
    • Penetration sleeves out of position — most often the sewer stack is 30–80 mm off the hydraulic drawing because the plumber set out from a different reference point than the slab set-out.
    • Termite barrier damage at penetrations — collars torn or displaced when conduit or pipework was installed after the barrier went down, breaking the continuous protected envelope.
    • Inadequate cover at edge beams — bars too close to the side of the formwork, often because the cage was lifted and dropped during set-out. Once poured, these bars are vulnerable to moisture ingress at the slab edge.

    Real example we've documented

    A recent Stockland Rivermont pre-pour at Caboolture showed bar chairs spaced at roughly 1.2 m through the centre of the main living-area panel — the bottom mesh was sagging to about 20 mm cover against the 30 mm called up for the slab's exposure classification. The report cited AS 3600 clause 4.10.3 (cover for durability) and the engineer's slab detail. The steel fixer added chairs in about 40 minutes before the truck arrived; left unfound, the shortfall was a corrosion-cracking risk within five to ten years — exactly the kind of item that later turns up in our common defects found at handover once the damage has surfaced.

    Why timing matters: the 24–48 hour window

    The pre-pour inspection has a tight window. Book too early and the steel fix is incomplete — penetrations not in, mesh not laid out, edge beam cages still loose. Book too late and the concrete truck is already on the way, leaving no time for the steel fixer to come back and correct anything we flag.

    The sweet spot is 24 to 48 hours before the scheduled pour. By then the steel fix is finalised, the plumber and electrician have completed rough-in, the termite barrier is in place and the formwork is braced for pour. If we identify defects, the site supervisor has a full working day to coordinate corrections without pushing the pour date. We turn the report around the same day with photos and clear rectification recommendations so the conversation with the builder is fact-based, not adversarial.

    Frequently asked questions

    When should I book a pre-pour inspection?

    Book as soon as your builder confirms the steel fix is complete and the pour date is locked in. The realistic window is 24–48 hours before the truck arrives — late enough that the cage, formwork and services are all in their final position, early enough that the steel fixer can come back and correct anything we flag without delaying the pour.

    What happens if we find defects on the day before the pour?

    We document each item with photos, location notes and an AS3600 / engineer's drawing reference, then send the report inside two hours so you can forward it straight to your site supervisor. Most issues — chair spacing, missing ligatures, cover shortfalls, penetration positions — are 30 to 90 minutes of work for the steel fixer or plumber and do not delay the pour.

    Does my builder have to let an independent inspector on site?

    Yes. As the owner under a HIA or Master Builders contract you have a contractual right to inspect at any stage, and QBCC guidance confirms independent third-party inspection is allowed at agreed hold points. We coordinate directly with the site supervisor and arrive in hi-vis and safety boots so the visit is straightforward.

    Do you check the termite barrier as well?

    Yes. We verify the termite management system installed against AS 3660.1 — perimeter and penetration barriers, joins, lapping at the slab edge, and that nothing has been damaged or displaced during plumbing rough-in. Termite barrier failures discovered post-handover are expensive and not always covered, so this is one of the higher-value checks at pre-pour.

    What does the report look like?

    A PDF delivered same day, typically 15–25 pages, with an executive summary, photo-tagged defect list, AS3600 / engineer's drawing references, and a recommended action for each item (rectify before pour, monitor, or accept). Format is the same as our other inspection reports — sample available on request.

    How much does a pre-pour inspection cost?

    A pre-pour slab inspection is $550 including GST for a standard residential slab across Brisbane and the Moreton Bay corridor. That covers the full attendance, the same-day photo-tagged report with AS 3600, AS 2870 and AS 3660.1 references, and a follow-up call to walk you through anything flagged. Larger or double-storey footing systems are quoted individually — call us with the plan size and we'll confirm before you book.

    Do you inspect waffle-pod slabs as well as conventional raft slabs?

    Yes. Waffle-pod and conventional stiffened-raft slabs are both engineered to AS 2870 and both are inspected pre-pour. On a waffle pod we verify the pod layout, rib widths and the top and bottom mesh position against the engineer's detail; the failure modes differ from a conventional raft (pod float, ribs pinched narrow, mesh laps short over the pods) but the standard and the check discipline are the same. Estates across Caboolture, Narangba and the wider Moreton Bay growth corridor use both systems, so we're on them most weeks.

    Most clients who book a pre-pour inspection book us through to handover. See our construction stage inspections for the full build journey, our Caboolture building inspection page if you're building in the Moreton Bay corridor, or the common defects found at handover to see what these pre-pour items become if they're missed.

    Our 100-point pre-pour checklist

    Our 100-point pre-pour inspection covers residential slabs and footing systems. Every item is checked against the governing Australian Standards and the project's engineering drawings, soil classification and approved working drawings. The list is general in nature — each inspection follows the specific approved documents for that build.

    1. Documentation & Approvals(8)
    • Current engineering drawings (slab/footing design) on site and referenced
    • Soil classification report available and matches the footing design (AS 2870)
    • Design certification for the footing system sighted where applicable
    • Most recent drawing revision confirmed before works commenced
    • Approved working drawings on site and consistent with the engineering
    • Site classification and wind classification consistent across documents
    • All discrepancies between documents reported before proceeding
    • Engineer's hold points identified and required inspection notice given
    2. Site Preparation & Earthworks(10)
    • Topsoil and vegetation stripped from the slab footprint
    • Cut and fill completed per the approved site works plan
    • Controlled fill placed and compacted in accordance with AS 3798 where applicable
    • Compaction test results available for filled platforms where specified
    • Pad level and extent consistent with the working drawings
    • Excavations free of water, loose material and debris
    • Footings founded at the specified depth into the specified bearing material
    • Founding conditions consistent with the soil classification — variations reported
    • Batters and adjoining excavations stable and clear of the footing zone
    • Surface drainage directed away from the building platform during construction
    3. Setout & Dimensions(8)
    • Slab setout checked against the site plan — boundary setbacks confirmed
    • Overall slab dimensions checked against the working drawings
    • Diagonals checked — slab square within tolerance
    • Finished floor level consistent with the approved plans
    • Step-downs formed at the specified locations (garage, alfresco, porch, wet areas) at the specified depths
    • Re-entrant corners and offsets formed per the plan
    • Attached slabs (patio / pad / alfresco) formed per the engineering detail
    • Penetration setout consistent with the hydraulic and electrical layouts
    4. Formwork(8)
    • Formwork alignment consistent with the engineer's plan
    • Form heights produce the specified slab thickness and beam depths
    • Formwork level and straight within tolerance
    • Formwork adequately braced and staked against movement during the pour
    • Edge boards secure with no gaps that would cause slurry loss
    • Step-down and rebate forms (including brick rebates) installed as detailed
    • Boxouts and blockouts located per the plan
    • Formwork clean and free of debris ahead of the pour
    5. Sand Bed & Vapour Membrane(8)
    • Sand bed installed at the specified minimum thickness (typically 50 mm) and evenly graded
    • Vapour membrane minimum 0.2 mm polythene installed under the full slab area
    • Membrane laps minimum 200 mm
    • All membrane joints and penetrations sealed with approved tape
    • Membrane free of punctures and tears — damage patched with approved material
    • Membrane turned up at slab edges as specified
    • Membrane carried through / under beams as specified in the design
    • Membrane protected from damage by reinforcement supports and foot traffic
    6. Termite Management (AS 3660.1)(6)
    • Termite management system installed per AS 3660.1 and the approved design
    • System type matches the certificate / specification (physical, chemical or combined)
    • Perimeter system installed and continuous
    • Penetration collars fitted to all slab penetrations
    • Installer's certificate / documentation available
    • System protected from damage prior to and during the pour
    7. Beams, Trenches & Pod Systems(10)
    • Edge beam width and depth per the engineering details
    • Internal beams located, sized and deepened per the plan
    • Trench sides stable with no collapse or contamination
    • Trench bottoms clean, dry and at the specified founding depth
    • Stiffened raft / footing geometry matches the design (AS 2870)
    • Waffle pod layout per the design — pod size, spacing and rib widths confirmed
    • Pods clean, undamaged and correctly supported
    • Rib and beam continuity maintained around penetrations and step-downs
    • Deepened edge beams at step-downs and load positions per the detail
    • Piers / pads (where specified) located, sized and founded per the design
    8. Reinforcement — Mesh(12)
    • Mesh grade and sheet size per the engineer's schedule
    • Mesh laps at the specified minimum (typically 225 mm / two squares)
    • Corner laps complete and tied
    • Mesh supported on bar chairs at spacing that prevents sag between supports
    • Bar chair size achieves the specified top cover (typically 30–40 mm residential, per AS 3600 / AS 2870)
    • Chairs on membrane fitted with base plates to prevent puncture
    • Mesh clean — free of mud, oil and loose scale
    • Additional mesh / trimming bars at re-entrant corners as specified
    • Additional bars over internal beams and load points per the schedule
    • Trench mesh in strip footings of the specified width and grade
    • Trench mesh continuity maintained around penetrations
    • Mesh terminated with the specified cover to all edges
    9. Reinforcement — Bars & Cages(10)
    • Edge beam cage bar count, diameter and grade per the schedule
    • Ligature size and spacing per the schedule
    • Bar laps at the specified lap length / development length
    • Corner and intersection bars (L-bars) installed for continuity
    • Side and bottom cover to cages per the design (typically 40–50 mm to ground)
    • Cages supported on spacers — not resting on ground or membrane
    • Starter bars / dowels at step-downs and connections per the detail
    • Reinforcement around penetrations trimmed per the detail
    • Steel free of excessive rust, contamination or damage
    • All reinforcement tied and secure against displacement during the pour
    10. Services & Penetrations(10)
    • Plumbing penetrations positioned per the hydraulic layout (within the specified tolerance)
    • Under-slab drainage installed, bedded and — where required — tested/certified before cover (AS/NZS 3500)
    • Pipes through the slab sleeved or lagged as specified
    • Puddle flanges / riser heights appropriate for the finished levels
    • Electrical conduits positioned per the layout and secured
    • Conduits and pipes do not displace reinforcement or reduce cover below minimum
    • Services isolated from termite pathways per the system design
    • No unapproved chases or voids compromising the slab section
    • Penetration clusters reinforced / trimmed per the engineering detail
    • Gas and other services located and protected as specified
    11. Pour Readiness & Quality Provisions(10)
    • Specified concrete grade and slump confirmed for order (per the engineer's notes)
    • Concrete supplier dockets to be retained for records
    • Access for placement adequate — pump/chute reach without displacing steel
    • Final cover walk-through completed — no steel touching forms or membrane
    • Weather conditions and hot/cold weather provisions considered for the pour
    • Control / articulation joint locations planned per the design (AS 2870)
    • Curing method confirmed (curing compound or moist curing for the specified period)
    • Engineer's / certifier's hold point inspection completed where required
    • Date of inspection recorded and checklist retained
    • Completed checklist signed by the responsible inspector

    Want the detail behind every item? Read our full pre-pour slab inspection guide — what each check looks like on site, why it matters, and the 15 red flags that mean you shouldn't let the trucks turn up.

    Get It Right Before the Pour

    Book before concrete pour — usually 24–48 hours notice

    Schedule your pre-pour inspection while corrections are still possible. It's the smart foundation for your build.

    Your build, stage by stage

    Every new home moves through the same inspection sequence. See where this stage fits and jump to the ones before and after it.

    1. 1Pre-Pour
    2. 2Slab
    3. 3Frame & Pre-Plaster
    4. 4Enclosed & Waterproofing
    5. 5Practical Completion
    6. 6Handover (2nd)
    7. 7Warranty (11-month)
    07 3180 8041